Power plants are built on debt — a story of project finance

Building a single 20 MW solar plant costs more than 20 billion won. That money all goes out before any electricity is sold, and it comes back bit by bit over 20 years as the electricity is sold. That is why a bank's credit officer looks first not for a thick business plan but for a one-page document stating 'to whom, at what price and for how many years' the power will be sold.

Published

Contents (7)
  1. 01What does one 20 MW plant cost?
  2. 02What does the bank trust when it lends?
  3. 03By what road does the money come back?
  4. 04Do the three add up to revenue?
  5. 05Where numbers trip you up
  6. 06So what should be written on that one page?
  7. 07Words in this piece

The bank's credit officer didn't leaf through the thick business plan but looked for a one-page document first. A single 20 MW solar plant costs more than 20 billion won, but that number is not what the bank wants to see first.

One page before the thick plan
20MW

Across the table sits the head of a development company that has secured every permit and Grid connection Grid connection is the work of linking a new power plant to the network so its power can actually be delivered. Glossary →. The CEO asks, "How much can you lend us?" The credit officer asks back, "Has it been settled to whom, at what price and for how many years you'll sell the electricity?"

The officer answered a question with a question, but the question is the answer. The moment a power plant is built, the money is all spent, and it comes back bit by bit over 20 years as the electricity is sold. So in a bank's eyes, "a project cost of 20 billion won" and "a unit price of so many won, a contract of so many years" belong in the same sentence.

What does one 20 MW plant cost?

The facility cost of ground-mounted solar, surveyed by the Korea Energy Economics Institute in 2024, falls as plants get bigger. For the 20 MW class it was about 1.06 million won per kW (1,058,000 won). Multiply that by 20 MW and you get about 21.16 billion won.Source 1Korea Energy Economics Institute (KEEI), *Basic Research Report 2024-22* (「기본연구보고서」; unofficial translation), pp.14·16·36·45·49facility costs from the 2024 survey (thousand won/kW). Ground-mounted solar 100 kW class 1,303· 1 MW class 1,281· 3 MW class 1,157· 20 MW class 1,058; onshore wind 20 MW class 2,928. KEPCO grid connection costs are included in the indirect costs of the facility cost (p.34); land purchase and site lease costs are in a separate section. Values in won in the text are Renuary estimates. Offshore wind is based on a sample of 5 projects.See in sources →

Show the numbers
Ground-mounted solar sizeFacility cost per kW
100 kW classabout 1.3 million won
1 MW classabout 1.28 million won
3 MW classabout 1.16 million won
20 MW classabout 1.06 million won

Data Korea Energy Economics Institute (KEEI), Basic Research Report 2024-22 (2024 survey) · values in millions of won rounded by© Renuary

These surveyed facility costs include the cost of connecting to KEPCO's grid. Land is separate, so the actual project cost can be higher.Source 1Korea Energy Economics Institute (KEEI), *Basic Research Report 2024-22* (「기본연구보고서」; unofficial translation), pp.14·16·36·45·49facility costs from the 2024 survey (thousand won/kW). Ground-mounted solar 100 kW class 1,303· 1 MW class 1,281· 3 MW class 1,157· 20 MW class 1,058; onshore wind 20 MW class 2,928. KEPCO grid connection costs are included in the indirect costs of the facility cost (p.34); land purchase and site lease costs are in a separate section. Values in won in the text are Renuary estimates. Offshore wind is based on a sample of 5 projects.See in sources →

Bigger is cheaper — capex per kW (2024 survey)
Solar 100kW~1,300k wonSolar 1MW~1,280k wonSolar 3MW~1,160k wonSolar 20MW~1,060k wonWind 20MW~2,930k won0k1000k2000k3000k

From KEEI basic research report 2024-22, 2024 survey (note 1), rounded to 10,000 won. Grid connection cost is included; land may be extra.

Read this figure as text

Five horizontal bars of capex per kW, rounded to 10,000 won. Solar at 100 kW about 1,300,000 won, 1 MW about 1,280,000, 3 MW about 1,160,000, 20 MW about 1,060,000. The orange bar at the bottom, for comparison, is onshore wind at 20 MW, about 2,930,000 won. Grid connection cost is included; land may be extra.

Figure page · cite · download →

Wind is far more expensive. In the same survey, onshore wind in the 20 MW class came to about 2.93 million won per kW. Facility costs for offshore wind in Korea came out at around 5.5 billion to 6.5 billion won per MW.Source 1Korea Energy Economics Institute (KEEI), *Basic Research Report 2024-22* (「기본연구보고서」; unofficial translation), pp.14·16·36·45·49facility costs from the 2024 survey (thousand won/kW). Ground-mounted solar 100 kW class 1,303· 1 MW class 1,281· 3 MW class 1,157· 20 MW class 1,058; onshore wind 20 MW class 2,928. KEPCO grid connection costs are included in the indirect costs of the facility cost (p.34); land purchase and site lease costs are in a separate section. Values in won in the text are Renuary estimates. Offshore wind is based on a sample of 5 projects.See in sources → Compared per MW, offshore wind costs five to six times as much as 20 MW-class ground-mounted solar. Even for a plant of the same size, building it at sea changes the number of digits in the price.

As projects grow, the numbers outrun the imagination. The Shinan Ui offshore wind farm in South Jeolla Province, which signed its financing agreements in April 2026, is 390 MW with a total project cost of 3.4 trillion won.Source 2Financial Services Commission, press release (2026-04-09)financing agreements for the Shinan Ui offshore wind farm. The loan interest rate has not been disclosed.See in sources → That is enough money to build about 160 of the 20 MW solar plants above. But this total project cost was calculated in a different document, over a different scope, from the facility cost survey above, so it is not divided per MW and compared directly with the 5.5 billion to 6.5 billion won above. Few companies have this much money piled up on their own.

What does the bank trust when it lends?

Back to that table. What the bank looks at is not the bank account of the CEO's company. A separate company is set up just for the one power plant (a special purpose vehicle), and the bank lends based only on the money that company will earn in the future. This method is PF (project financing) Project financing lends money on the strength of the cash a single project will earn, not on a company's credit. Glossary → (PF). PF is a way of borrowing on the strength not of a company's credit but of "the money this plant will earn," and repaying with that money.

Most of Shinan Ui's 3.4 trillion won was debt. The money the owners put in themselves (equity) was 510 billion won (15%), and the remaining 2.89 trillion won (85%) is loans. The loans split again into 2.5 trillion won of senior debt, repaid first, and 390 billion won of subordinated debt, repaid later.Source 2Financial Services Commission, press release (2026-04-09)financing agreements for the Shinan Ui offshore wind farm. The loan interest rate has not been disclosed.See in sources →

Project cost in three layers — order of repaymentExample numbers
Senior debt1. Repaid firstSubordinated debt2. NextEquity3. Last — owners keep what’s left

Layer sizes are examples; real splits vary by project.

It resembles buying a home with 15% of your own money and an 85% loan on top. The difference is that the money to repay comes not from a house but from the wind that will blow over the next 20 years. So the bank has to confirm the path by which that wind turns into money. That is why the credit officer looked for a contract before the business plan. Without a contract, the wind is still just wind.

By what road does the money come back?

Once the plant starts running, it is paid two prices. One is the price of electricity. The other is the price of the Renewable Energy Certificate (REC (Renewable Energy Certificate) A REC is the issuing and trading unit of a certificate proving renewable supply. Renewable generators earn income from selling RECs, apart from selling electricity. Glossary →), a certificate bought and sold that carries the value of "having been made from renewable energy" (its environmental attribute).

Sell only electricity into the market, and you get the wholesale price (SMP (System Marginal Price) SMP is the energy price set for each trading hour in the power market. It is the highest generation price among the generators eligible to set the price in that hour. Glossary →), which changes every hour. The SMP for all of 2025 (mainland and Jeju combined) published by the Korea Power Exchange was 112.72 won per kWh.Source 6Korea Power Exchange (KPX), *Annual System Marginal Price, Mainland and Jeju Combined* (「육지 제주 통합 연도별 계통한계가격」, Public Data Portal 15151997, revised 2026-10-13; unofficial translation)combined 2025 value 112.72 won/kWh. The MWh conversion (about 110,000 won) is a Renuary calculation.See in sources → Converted to MWh, that is about 110,000 won.

Sell RECs on the spot market, where they are bought and sold as needed, and they get that day's price. Taking a simple average of the 12 monthly REC spot averages in Korea Power Exchange statistics, 2025 came to 71,920 won. In 2024 it was 76,181 won.Source 4Korea Power Exchange (KPX), *2025 Electricity Market Statistics* (「2025년도 전력시장 통계」; unofficial translation), Table 3-3 (REC spot market monthly averages, combined). The 12-month simple average is a Renuary calculation.See in sources →

Roughly, then, in 2025 about 110,000 won was attached to 1 MWh of electricity and about 70,000 won to one REC. But both prices rise and fall from year to year, and the REC price from month to month. This swing is exactly what banks dislike. You cannot hang a loan that must be repaid over 20 years on income whose price changes every year. So a contract that locks in income in advance is needed. There are two main routes.

  • Government fixed-price auction (Fixed-price contract auction In a fixed-price contract auction, renewable developers bid for a government-set volume, and winners lock in a combined power-plus-REC price for the long term. Glossary →): the plant receives a fixed price for the combined SMP and REC over a long period. The average winning bid in the 2026 Round 1 solar auction was 146,920 won per MWh. That is a basis that adds the price of one REC to the price of 1 MWh of electricity (SMP+1REC).Source 5Korea Energy Agency, notice (2026-09-29), Attachment 1results of the 2026 Round 1 competitive bidding for solar fixed-price contracts.See in sources →
  • A long-term power purchase agreement (PPA (Power Purchase Agreement) A PPA is a long-term power sale contract. In Korea the typical form is direct power trading (direct PPA): renewable power supplied to companies and others outside the power market. Glossary →) with a company: the plant signs a contract of around 20 years at a set price with a company that wants to buy electricity.

An REC is a unit assigned by multiplying the amount of electricity, in MWh, by a weighting.Source 7Ministry of Climate, Energy and Environment, *Guidelines on the Management and Operation of the Renewable Portfolio Standard and the Renewable Fuel Standard* (「재생에너지 공급의무화제도 및 연료 혼합의무화제도 관리ㆍ운영지침」, Ministry of Climate, Energy and Environment Notice No. 2026-233, effective 2026-09-18; unofficial translation), Art. 3, item 6a REC is a unit assigned by multiplying the amount of renewable electricity, in MWh, supplied from an eligible facility by a weighting (Korean Law Information Center).See in sources → So the winning-bid basis is a price pairing 1 MWh of electricity with one certificate. It is a different year from the 2025 market estimate above (about 110,000 won and about 70,000 won). One is an average of prices won in auctions, the other a rough estimate of market rates. We do not say which is more expensive from the size of the numbers alone.

Either way, a one-page contract sets the floor of the next 20 years of income. That floor is what the bank wants to see.

Do the three add up to revenue?

There is a common misconception. If a plant earns three prices, the SMP, the REC and the PPA price, then revenue must be all three added together.

You cannot sell the same 1 MWh of electricity twice. If a plant has signed a PPA with a company, that contract price replaces receiving the SMP and the REC separately. If it has won a fixed-price auction, the winning bid fixes the sum of SMP and REC. What a plant chooses is "where to sell," that is, its route to market.

It can sell straight into the market, win a fixed-price auction, or sign a PPA with a company. Only when it sells straight into the market does it receive both the SMP and the REC spot price as they are, and the PPA price is not added on top. Depending on the contract, the plant may also split things up, selling the electricity into the market and handing only the RECs to a company. Even then, it does not get paid twice for the same share.

Route to marketWhat the plant receivesSwing
Straight into the marketSMP + REC spot priceLarge
Fixed-price auction(SMP+REC) total, fixedSmall
Corporate PPAContract priceDepends on contract terms

Data compiled by© Renuary

Where numbers trip you up

Numbers in this field can carry the same name yet be made in different ways. In practice, there are three common snags.

  • How the average was made. The REC price above is an unweighted average of the 12 monthly averages. It does not give more weight to months with more trading. An annual SMP figure, too, can only be compared once you state whether it is mainland, Jeju or combined. So "about 110,000 won for electricity + about 70,000 won for a REC" is a rough estimate for gauging weight, not the actual income of any one plant.
  • Winning bids and market rates are in different units. A fixed-price winning bid is a basis that combines the SMP and one REC. Compare it directly with the market SMP or REC rate alone and you get it wrong. Even when comparing it with a market estimate that adds the two, first check that the values are from the same year and calculated the same way.
  • A policy interest rate is not a private-sector rate. The Korea Energy Agency's interest rate for new and renewable energy policy loans in Q4 2026 is 2.75% (it changes every quarter).Source 3Korea Energy Agency, notice (2026-09-29)loan interest rate for new and renewable energy policy loans, Q4 2026.See in sources → These loans go only to projects that meet set requirements. The interest rate on the Shinan Ui loans has not been disclosed.

Even numbers with the same name mean different things depending on what was bundled and how.

So what should be written on that one page?

This is how money flows through a power plant. For a 20 MW solar plant, more than 20 billion won (the estimate above) goes out all at once during construction. Shinan Ui filled most of that with debt. Then for the next 20 years the plant sells electricity and RECs, repays debt every year, and what is left becomes the owner's return. If income swings, the risk of failing to repay rises, and by that much, interest rates go up or loans shrink.

A big outlay up front, small returns each yearExample numbers
Build costYears →Grey = debt service · Orange = owners

Bar sizes and loan term are illustrative.

The roughly 21.1 billion won estimated above (excluding land) is the money going out. The one-page contract is the paper that states how that money will come back over 20 years. That is why "a unit price of so many won" and "a contract of so many years" at the dealmaking table are not haggling but the floor of 20 years of income.

A few days later, the CEO opens the meeting room door again, holding a sheet with the three boxes filled in: "to whom, at what price, for how many years." This time, it is the credit officer who opens the business plan first.

Words in this piece

  • PF (project financing) Project financing lends money on the strength of the cash a single project will earn, not on a company's credit. Glossary → — a way of borrowing on the strength of the money one power plant will earn, instead of a company's credit, and repaying with that money.
  • REC (Renewable Energy Certificate) A REC is the issuing and trading unit of a certificate proving renewable supply. Renewable generators earn income from selling RECs, apart from selling electricity. Glossary → — a certificate bought and sold that carries the value of "having been made from renewable energy" (environmental attribute). It can be bought and sold separately from the electricity.
  • SMP (System Marginal Price) SMP is the energy price set for each trading hour in the power market. It is the highest generation price among the generators eligible to set the price in that hour. Glossary → — the wholesale price of electricity in the electricity market, set every hour. Sell straight into the market and this is the price you get.
  • Fixed-price contract auction In a fixed-price contract auction, renewable developers bid for a government-set volume, and winners lock in a combined power-plus-REC price for the long term. Glossary → — a program under which a plant that wins a government auction receives a fixed price for electricity and RECs combined over a long period.
  • PPA (Power Purchase Agreement) A PPA is a long-term power sale contract. In Korea the typical form is direct power trading (direct PPA): renewable power supplied to companies and others outside the power market. Glossary → — a contract signed with a company that wants to buy electricity, with the price and term set in advance.
  • Route to market — the choice of where a plant sells its electricity and RECs: the market, a fixed-price auction, or a corporate PPA.
Sources (7)

Sources

  1. DataKorea Energy Economics Institute (KEEI), *Basic Research Report 2024-22* (「기본연구보고서」; unofficial translation), pp.14·16·36·45·49 ↩facility costs from the 2024 survey (thousand won/kW). Ground-mounted solar 100 kW class 1,303· 1 MW class 1,281· 3 MW class 1,157· 20 MW class 1,058; onshore wind 20 MW class 2,928. KEPCO grid connection costs are included in the indirect costs of the facility cost (p.34); land purchase and site lease costs are in a separate section. Values in won in the text are Renuary estimates. Offshore wind is based on a sample of 5 projects.
  2. ReleaseFinancial Services Commission, press release (2026-04-09) ↩financing agreements for the Shinan Ui offshore wind farm. The loan interest rate has not been disclosed.
  3. ReleaseKorea Energy Agency, notice (2026-09-29) ↩loan interest rate for new and renewable energy policy loans, Q4 2026.
  4. DataKorea Power Exchange (KPX), *2025 Electricity Market Statistics* (「2025년도 전력시장 통계」; unofficial translation), Table 3-3 (REC spot market monthly averages, combined). The 12-month simple average is a Renuary calculation. ↩
  5. ReleaseKorea Energy Agency, notice (2026-09-29), Attachment 1 ↩results of the 2026 Round 1 competitive bidding for solar fixed-price contracts.
  6. Korea Power Exchange (KPX), *Annual System Marginal Price, Mainland and Jeju Combined* (「육지 제주 통합 연도별 계통한계가격」, Public Data Portal 15151997, revised 2026-10-13; unofficial translation) ↩combined 2025 value 112.72 won/kWh. The MWh conversion (about 110,000 won) is a Renuary calculation.
  7. LawMinistry of Climate, Energy and Environment, *Guidelines on the Management and Operation of the Renewable Portfolio Standard and the Renewable Fuel Standard* (「재생에너지 공급의무화제도 및 연료 혼합의무화제도 관리ㆍ운영지침」, Ministry of Climate, Energy and Environment Notice No. 2026-233, effective 2026-09-18; unofficial translation), Art. 3, item 6 ↩a REC is a unit assigned by multiplying the amount of renewable electricity, in MWh, supplied from an eligible facility by a weighting (Korean Law Information Center).

Ask about this postQuestions shape the next pieces

Comments

  1. Loading…

Comments appear at once. Spam, abuse and personal data are removed. Two links at most.

Contents (7)

  1. 01What does one 20 MW plant cost?
  2. 02What does the bank trust when it lends?
  3. 03By what road does the money come back?
  4. 04Do the three add up to revenue?
  5. 05Where numbers trip you up
  6. 06So what should be written on that one page?
  7. 07Words in this piece

All menus

Search

Articles

Data

Rules

History

Glossary

Renuary