Five ways to buy renewable energy — how the green premium, RECs, PPAs and self-consumption differ

There are five main ways for a company to have its renewable energy use recognized. With four of them, the electricity that reaches the factory is the same. So why do three companies pick different routes? We follow what each one buys and how long it is locked in.

Published

Four of five
Across the five routes, the electricity that arrives is the same
Contents (8)
  1. 01If the electricity is the same, what are you choosing?
  2. 02If next year's record is urgent, the top two lines
  3. 03To lock in a price for a long time, the middle two lines
  4. 04How is a third-party PPA different from a direct PPA?
  5. 05With a big roof, the bottom line
  6. 06When you hear an unfamiliar name
  7. 07Where did the three companies land?
  8. 08Words in this piece

Staff at three companies have the same guide page open in front of them. It lists, in five lines, the routes by which a company can be recognized as having used renewable energy: the green premium, REC purchases, third-party PPAs, direct PPAs and self-consumption.

One thing is odd. With four of the five, the electricity that comes into the factory is the same. All of it is mixed electricity that has traveled over the same power grid (the transmission and distribution lines that carry electricity from power plants to factories). Even so, the three people's fingers land on different lines. If the electricity is the same, what are they choosing?

If the electricity is the same, what are you choosing?

Translate the five lines into grocery shopping and they look like this.

  • You buy the same vegetables at your usual supermarket, and add an "organic share" surcharge at the checkout.
  • Separately from the vegetables, you buy only a certificate saying "grown organically."
  • You sign up for regular deliveries from one farm at the same price for several years, with a shop in between.
  • You sign up for the same regular deliveries directly with the farm.
  • You plant a vegetable patch in your yard.

There is one place where the analogy breaks down. Vegetables can be bagged separately by the field they came from, but electricity bought from outside arrives mixed over the same power grid whichever route you buy it by. So the difference among the five routes lies not in the electricity but in what you buy and how long you are locked in.

What you get at the end of each of the five routes is a "record." It is an official count of the renewable share of the electricity a company used, recognized as such. In Korea, Korean RE100 (K-RE100) recognizes this record, and these five are the main routes that the Korea Energy Agency describes.Source 1Korea Energy Agency, New and Renewable Energy Center, *K-RE100 Guide* (「K-RE100 안내」; unofficial translation)· *Regulation on Support for Renewable Energy Facilities, etc.* (「재생에너지 설비의 지원 등에 관한 규정」, Notice No. 2026-272, effective 2026-10-27; unofficial translation), Art. 68-2(1) (items 1 to 5, the five routes· item 6, other matters recognized by the minister).See in sources →

If next year's record is urgent, the top two lines

A parts supplier does not use much electricity. It needs a record for next year right away, but it cannot face a contract that locks it in for several years. The staff member's finger goes to the top two lines.

The Green premium A green premium is a scheme in which a buyer pays extra on top of its power bill and is recognised as having used that much renewable electricity. Glossary → has the lowest bar. The company keeps using the same Korea Electric Power Corporation (KEPCO) electricity it always has, pays a surcharge for a renewable share, and gets that much use recognized. The surcharge is paid to KEPCO.Source 1Korea Energy Agency, New and Renewable Energy Center, *K-RE100 Guide* (「K-RE100 안내」; unofficial translation)· *Regulation on Support for Renewable Energy Facilities, etc.* (「재생에너지 설비의 지원 등에 관한 규정」, Notice No. 2026-272, effective 2026-10-27; unofficial translation), Art. 68-2(1) (items 1 to 5, the five routes· item 6, other matters recognized by the minister).See in sources → Like the surcharge at the supermarket checkout, it is not directly tied to any power plant.

The second line is buying only the certificate. A Renewable Energy Certificate (REC (Renewable Energy Certificate) A REC is the issuing and trading unit of a certificate proving renewable supply. Renewable generators earn income from selling RECs, apart from selling electricity. Glossary →) is a certificate that carries the value of "made from renewable energy" (the environmental attribute) and is bought and sold. You only need to buy as many as you need, so it is easy to match the volume. In exchange, the price moves with the market, so there is no guarantee that a budget that works this year will work next year.

Both routes let you move on a short horizon. In exchange, they are not directly tied to building any particular new power plant.

To lock in a price for a long time, the middle two lines

For a large materials company, the situation is the reverse. A few years from now it will need large volumes every year, and it wants that price to stay steady for a long time. Its finger goes to the middle two lines, the power purchase agreement (PPA (Power Purchase Agreement) A PPA is a long-term power sale contract. In Korea the typical form is direct power trading (direct PPA): renewable power supplied to companies and others outside the power market. Glossary →).

A PPA is a regular delivery deal with one farm. The buyer promises to purchase a specific power plant's electricity at a set price for several years. The generation company gains a long-term outlet and can use that promise to win over banks, and the corporate buyer can lock in its electricity price for a long time.

The longer the lock-in, the more there is to work out in advance. These are not things you can settle at a first meeting.

  • When does supply start?
  • If generation falls short or runs over, how is the money squared up?
  • Who pays the grid usage fee (the price of renting the power grid)?
  • What happens if one side quits partway through?

How is a third-party PPA different from a direct PPA?

The two middle lines have similar names. In both, the electricity also reaches the factory over the same power grid. What differs is who stands in the middle.

  • In a third-party PPA, KEPCO stands in between. The notice calls it a "power purchase agreement through an electric sales business entity."Source 2Ministry of Climate, Energy and Environment, *Regulation on Support for Renewable Energy Facilities, etc.* (「재생에너지 설비의 지원 등에 관한 규정」, Notice No. 2026-272, effective 2026-10-27; unofficial translation), Art. 67(3) (operating bodiesgreen premium and power purchase agreements through an electric sales business entity: Korea Electric Power Corporation; REC purchases and self-consumption: New and Renewable Energy Center; direct PPAs: Korea Power Exchange)· Art. 69(1) (electricity consumers submit usage details through the management system) and (4) (for the green premium, the operating body submits the payment results).See in sources → Once the corporate buyer and the generation company agree on terms, KEPCO, as the business that sells electricity, supplies that electricity to the corporate buyer. "Going through KEPCO" means KEPCO takes the contracting and selling role. The path the electricity travels is the same power grid as in a direct PPA.
  • A direct PPA has no KEPCO in it. A business allowed to sell electricity directly to companies, a renewable electricity supplier (unofficial translation), contracts directly with the corporate buyer.
Two routes from plant to factory

Only the counterparty differs; grid charges apply on both routes.

© Renuary

Which is better differs from company to company. If a direct contract feels like a burden, the route with KEPCO in between catches the eye first; if the company wants to shape the price and terms itself, the direct route does.

With a big roof, the bottom line

The finger of a factory with a big roof goes to the bottom line, self-consumption. Like a vegetable patch in the yard, the company puts solar PV on the factory roof or on spare land and uses that electricity itself. It is the only one of the five lines where the electricity is used right inside the building without passing through the power grid.

If the installation cost is a burden, there is also an arrangement in which an outside company installs the equipment and sells the electricity it produces to the company. It is commonly called an on-site PPA. Here the questions are whether the building's structure is safe, whether there is a right to use the roof, who handles waterproofing and upkeep, and who owns the equipment.

Having PPA in the name does not settle which line it belongs on. With KEPCO in between, it is a third-party PPA; signed directly with a renewable electricity supplier, it is a direct PPA. An on-site PPA, which buys electricity from equipment on the roof, has to be sorted into its line with the contract open on the table. Besides the five routes, the notice also has one more slot: "other methods recognized by the minister."Source 1Korea Energy Agency, New and Renewable Energy Center, *K-RE100 Guide* (「K-RE100 안내」; unofficial translation)· *Regulation on Support for Renewable Energy Facilities, etc.* (「재생에너지 설비의 지원 등에 관한 규정」, Notice No. 2026-272, effective 2026-10-27; unofficial translation), Art. 68-2(1) (items 1 to 5, the five routes· item 6, other matters recognized by the minister).See in sources →

When you hear an unfamiliar name

In the news and at industry events, you often hear names that fall outside the five lines.

Faced with names like these, ask two things first. Which of the five routes does it attach to, and can it be used in Korea now?

In practice, there is one more snag. The five routes are run by different bodies. KEPCO handles the green premium and third-party PPAs, the Korea Energy Agency's New and Renewable Energy Center handles REC purchases and self-consumption, and the Korea Power Exchange (KPX) handles direct PPAs. Still, there is a single window for submitting the record. The company submits its usage details itself through the agency's management system; only for the green premium does KEPCO pass on the payment results on its behalf.Source 2Ministry of Climate, Energy and Environment, *Regulation on Support for Renewable Energy Facilities, etc.* (「재생에너지 설비의 지원 등에 관한 규정」, Notice No. 2026-272, effective 2026-10-27; unofficial translation), Art. 67(3) (operating bodiesgreen premium and power purchase agreements through an electric sales business entity: Korea Electric Power Corporation; REC purchases and self-consumption: New and Renewable Energy Center; direct PPAs: Korea Power Exchange)· Art. 69(1) (electricity consumers submit usage details through the management system) and (4) (for the green premium, the operating body submits the payment results).See in sources →

Where did the three companies land?

Gather the five lines on one page and they look like this.

RouteWhat you buyHow long you are locked inSuits
Green premiumAdd a surcharge to the KEPCO electricity tariff and get renewable energy use recognizedShort, year by yearCompanies that need a record first
REC purchaseBuy only certificates that carry the environmental attributeShort, as much as neededCompanies that want to match volumes flexibly
Third-party PPABuy a generation company's electricity for a long time, with KEPCO in betweenLongCompanies that want long-term sourcing but find a direct contract a burden
Direct PPASign a long contract directly with a renewable electricity supplierLongCompanies that want large volumes for a long time at a locked-in price
Self-consumptionInstall equipment on your own land or roof and use the power yourselfAs long as the equipment lastsCompanies with a site to use

Contract length and terms vary from deal to deal.

Data Renuary's plain-language version of the Korea Energy Agency's guide to K-RE100 implementation routes© Renuary

Turn the table into a map with two axes, and you can see why the three companies went different ways. The horizontal axis is how long you are locked in; the vertical axis is how close you are to a specific power plant.

Five ways on one map — how long, how close
Tied in longer → plant lifetimeShort↑ Closer to a plant — our own roofGreen premiumREC purchaseThird-party PPADirect PPASelf-generationParts supplierMaterials makerWide-roof factory

Positions show the character of each route, not measurements. Orange houses mark where the three companies from the opening land.

Read this figure as text

The horizontal axis is how long you are tied in (short → the life of the plant); the vertical axis is how close you are to a specific plant (higher is closer, the top being your own roof). Green premium and REC purchases sit bottom-left: short and not tied to a plant. Third-party and direct PPAs sit middle-right, tied in for long. Self-generation is top-right. The three orange houses are the choices of the three companies at the start of the article: the parts supplier bottom-left, the large materials company in the PPA area, the factory with a big roof in self-generation. Positions are conceptual, not measured.

Figure page · cite · download →

The parts supplier starts at the lower left by securing next year's record, and prepares long-term sourcing for a few years out separately. The factory with the roof weighs self-consumption against an outside company's installation offer at the upper right. Facing the same electricity, the three simply chose how long to be locked in and how close to get to which power plant.

On the five lines of the guide page they first opened, the three fingers now rest in different places. The materials company heads to the middle right. When it sits down with a generation company whose supply start date fits, one box on the meeting-room whiteboard is still empty: at how much per kWh (kilowatt-hour, the unit for the amount of electricity used) to lock in the price.

Words in this piece

  • Green premium A green premium is a scheme in which a buyer pays extra on top of its power bill and is recognised as having used that much renewable electricity. Glossary → — a way to get renewable energy use recognized by paying a surcharge on top of the KEPCO electricity tariff. The surcharge is paid to KEPCO.
  • REC (Renewable Energy Certificate) A REC is the issuing and trading unit of a certificate proving renewable supply. Renewable generators earn income from selling RECs, apart from selling electricity. Glossary → — a certificate that carries the value of "made from renewable energy" (the environmental attribute) and is bought and sold. It is traded separately from the electricity.
  • PPA (Power Purchase Agreement) A PPA is a long-term power sale contract. In Korea the typical form is direct power trading (direct PPA): renewable power supplied to companies and others outside the power market. Glossary → — a contract to buy a specific power plant's electricity at a set price for several years. With KEPCO in between it is a third-party PPA; signed directly, it is a direct PPA.
  • Renewable electricity supplier — a business that can sell renewable electricity directly to companies. It is the selling side of a direct PPA.
  • Grid usage fee — the price of renting the power grid.
Sources (3)

Sources

  1. LawKorea Energy Agency, New and Renewable Energy Center, *K-RE100 Guide* (「K-RE100 안내」; unofficial translation)· *Regulation on Support for Renewable Energy Facilities, etc.* (「재생에너지 설비의 지원 등에 관한 규정」, Notice No. 2026-272, effective 2026-10-27; unofficial translation), Art. 68-2(1) (items 1 to 5, the five routes· item 6, other matters recognized by the minister). ↩
  2. LawMinistry of Climate, Energy and Environment, *Regulation on Support for Renewable Energy Facilities, etc.* (「재생에너지 설비의 지원 등에 관한 규정」, Notice No. 2026-272, effective 2026-10-27; unofficial translation), Art. 67(3) (operating bodies ↩green premium and power purchase agreements through an electric sales business entity: Korea Electric Power Corporation; REC purchases and self-consumption: New and Renewable Energy Center; direct PPAs: Korea Power Exchange)· Art. 69(1) (electricity consumers submit usage details through the management system) and (4) (for the green premium, the operating body submits the payment results).
  3. Climate Group, *RE100 Technical Criteria* (version 5.0, published 2025-03-24), §2.2 p.10 ↩"a purely financial transaction in which a corporate buyer assumes market risk … and receives energy attributes".

Ask about this postQuestions shape the next pieces

Comments

  1. Loading…

Comments appear at once. Spam, abuse and personal data are removed. Two links at most.

Contents (8)

  1. 01If the electricity is the same, what are you choosing?
  2. 02If next year's record is urgent, the top two lines
  3. 03To lock in a price for a long time, the middle two lines
  4. 04How is a third-party PPA different from a direct PPA?
  5. 05With a big roof, the bottom line
  6. 06When you hear an unfamiliar name
  7. 07Where did the three companies land?
  8. 08Words in this piece

All menus

Search

Articles

Data

Rules

History

Glossary

Renuary