Published
- Land without a single panel
- Six stages of a project that is traded before it makes any electricity
Contents (8)
- 01First, the landowner and the village
- 02There is more than one permit
- 03Why a power line next door may not be enough
- 04The six stages Mr. Park passes through
- 05The bank looks at the money the project will earn
- 06The day construction ends and the day of the first trade
- 07Back to that field
- 08Words in this piece
There is an empty field in a village in South Jeolla Province. Mr. Park, who heads a development company, wants to build a 20 MW solar PV plant there. A project on land like this, without a single panel on it, can still be bought and sold. It has not made any electricity yet, so what exactly carries a price? (Mr. Park and his field are a hypothetical case for explanation.)
What sets the price is not just the cost of panels. What matters is which of these has already been confirmed: the promise to use the land, the permits, the connection to the power grid, the financing and construction. Each one confirmed reduces the uncertainty over whether the plant can really be built. Even for plans of the same size, the risk a buyer takes on depends on which stage the project has reached.
First, the landowner and the village
Mr. Park does not yet have a power plant or a contract to sell power. The 20 MW is the amount of power the plant can deliver at a single instant, in other words its installed capacity. It says nothing about how much electricity has actually been produced and sold.
Mr. Park first asks the landowner about terms of use and talks with people in the village. The land-use promises exchanged here belong to individual contracts. But the landowner's consent does not mean a generation business license has been issued. A solar PV generation business must also be reviewed against license standards related to announcing the project in advance and hearing residents' views.Source 1Ministry of Government Legislation, Korean Law Information Center, *Electric Utility Act* (「전기사업법」), Art. 7 (effective 2026-09-18, checked 2026-10-30). Division between the minister and city or provincial licensing authorities, license standards, and the provision on gathering residents' views.See in sources →
There is more than one permit
Whether you may run a business making and selling electricity and whether you may build a facility on that land are two different questions. The first is the Generation licence A generation licence is the permit a person needs from the minister or a provincial governor to run a business that generates and sells electricity. Glossary →. The Electric Utility Act requires anyone who wants to run a generation business to obtain a license from the Minister of Climate, Energy and Environment or from the mayor or governor of the city or province, depending on size and other factors. The license standards also include whether the applicant has the financial and technical capacity to carry out the business and whether the business can proceed as planned.Source 1Ministry of Government Legislation, Korean Law Information Center, *Electric Utility Act* (「전기사업법」), Art. 7 (effective 2026-09-18, checked 2026-10-30). Division between the minister and city or provincial licensing authorities, license standards, and the provision on gathering residents' views.See in sources →
The second is a question about land. The National Land Planning and Utilization Act requires a permit from the competent authority for development activities set out in law, such as installing structures or changing the form and quality of land. The generation business license and the development activity permit (unofficial translation) are two checks with different purposes. So Mr. Park separately asks the local government with jurisdiction whether his site and type of facility need a permit and whether any exceptions apply.Source 2Ministry of Government Legislation, Korean Law Information Center, *National Land Planning and Utilization Act* (「국토의 계획 및 이용에 관한 법률」), Art. 56 (effective 2026-07-01, checked 2026-10-30). Installation of structures, changes to the form and quality of land, and the related exceptions.See in sources →
He also has to see whether the project is subject to an environmental impact assessment. The Environmental Impact Assessment Act lists energy development projects among the covered types, but whether a given project actually needs an assessment is decided by the type and size criteria in the Enforcement Decree. Once Mr. Park has fixed the site location and facility plan, he checks with the responsible agency whether an assessment is required and how to submit it.Source 3Ministry of Government Legislation, Korean Law Information Center, *Environmental Impact Assessment Act* (「환경영향평가법」), Art. 22 (effective 2025-10-23, checked 2026-10-30). The specific types and scope of covered projects are delegated to the Enforcement Decree, so the rule does not apply uniformly.See in sources →
Why a power line next door may not be enough
A permit alone does not let you start selling electricity. Electricity needs a road from the power plant to the people who use it. Mr. Park has to check with the body that runs the power grid he wants to connect to whether he can connect and on what terms. Connection talks, facility reinforcement and actual completion of the connection are separate stages.
A big road in front of your house does not mean you can put endless cars on it. Even if a transmission line runs past the field, whether the line and the equipment around it have room to spare is a separate question. Securing the land is not the same as securing a place to send the electricity.
He checks one item at a time: whether a connection is possible, whether equipment needs reinforcing, when he can connect, and who pays. If these answers are blurry, it is hard to set a start date for construction even with a permit in hand.
The six stages Mr. Park passes through
Spread out as a map, the road so far looks roughly like this. The six stages are an explanatory division meant to make the industry easier to understand; they are not a legal sequence that every power plant passes through in this order.
| Stage | Main things confirmed | Who confirms what, and with whom |
|---|---|---|
| Origination | Site, residents, project concept | The developer negotiates terms of use with the landowner and checks local opinion |
| Development and permitting | Generation business license, land use, environmental and connection reviews | The business operator applies to the licensing authority (the minister, or the mayor or governor of the city or province) for a generation business license, and checks the relevant development activity separately with the local government with jurisdictionSource 1Ministry of Government Legislation, Korean Law Information Center, *Electric Utility Act* (「전기사업법」), Art. 7 (effective 2026-09-18, checked 2026-10-30). Division between the minister and city or provincial licensing authorities, license standards, and the provision on gathering residents' views.See in sources → |
| Pre-construction | Financing, buyers of the power, construction preparations | The business operator finds investors, banks, power buyers and a contractor, and confirms each party's contract and review terms |
| Construction | Design, procurement, building | The contractor builds the facility, and the business operator checks the applicable construction plan and safety inspection procedures |
| Commercial operation | Inspection, start of power sales, report of business commencement | The electricity generation business entity reports the commencement of business to the licensing authority after it begins trading electricitySource 4Ministry of Government Legislation, Korean Law Information Center, *Electric Utility Act* (「전기사업법」), Art. 9 (effective 2026-09-18, checked 2026-10-30). Preparation period, commencement of business, and the distinction for reporting after an electricity generation business entity's first electricity trade.See in sources → |
| Operation and asset deals | Track record, operation, deals in equity or the project | The operating company records generation and maintenance performance, and the parties to a deal distinguish which rights are being bought and sold |
7 and 9 (effective 2026-09-18) · *National Land Planning and Utilization Act* (「국토의 계획 및 이용에 관한 법률」), Art. 56 (effective 2026-07-01) · *Environmental Impact Assessment Act* (「환경영향평가법」), Art. 22 (effective 2025-10-23).
Data *Electric Utility Act* (「전기사업법」), Arts·© Renuary
A shape-only sketch. The same 20 MW is worth different amounts at different steps.
At each stage, a buyer asks something different. For a project without a permit, the first question is whether it is feasible at all. Even with a permit, if the grid connection is still pending, the construction start date is uncertain. For a plant that has finished construction and is selling electricity, a buyer can look at its actual operating record as well as its expected revenue.
That is why a project's value is not set by the size of the facility alone. At each stage, the problems already solved and the problems the buyer will carry forward are different.
The bank looks at the money the project will earn
As construction nears, banks and investors come in. They have to estimate the money the power plant will earn in the future. Financing that is reviewed mainly on the money the project itself will earn, rather than only on the credit of the company as a whole, is PF (project financing) Project financing lends money on the strength of the cash a single project will earn, not on a company's credit. Glossary →.
Calling it PF does not make the money arrive on its own. Banks and investors look at how far the permits have gone, whether the project can connect to the power grid, and what revenue it can earn by selling electricity. They are asking again about what Mr. Park has confirmed, one by one, in the earlier stages.
The project can also sign a PPA (Power Purchase Agreement) A PPA is a long-term power sale contract. In Korea the typical form is direct power trading (direct PPA): renewable power supplied to companies and others outside the power market. Glossary → in advance with a party that will buy the electricity. A PPA is a contract that sets who will buy the electricity, for how long, at what price and on what terms, and its contents differ from project to project.
Construction has its own players as well. An EPC (engineering, procurement and construction) EPC is a contract under which one company designs a power plant, buys its equipment, builds it and hands it over. Glossary → company, which takes on engineering, procurement and construction as a package, builds the plant, and an O&M company runs and maintains it. When those who supply the money, those who buy the electricity, those who build and those who operate come in also differs from project to project.
The day construction ends and the day of the first trade
Saying construction is finished and saying the plant has started selling electricity are also two different things. The business operator first checks which construction plan, inspection and safety checks apply to its type of facility. An electricity generation business entity that has commenced business reports that fact to the licensing authority in the manner set by the Electric Utility Act. In particular, the law separately makes the entity's first electricity trade the reference point for the report of business commencement.Source 4Ministry of Government Legislation, Korean Law Information Center, *Electric Utility Act* (「전기사업법」), Art. 9 (effective 2026-09-18, checked 2026-10-30). Preparation period, commencement of business, and the distinction for reporting after an electricity generation business entity's first electricity trade.See in sources →
Even for a project that has finished construction, whether it has started selling and whether an operating record has built up are separate questions. What has been settled so far tells you more about where a project stands than the size of the power plant does.
Back to that field
In news of a "20 MW power plant project," 20 MW is only the size of the facility. That number alone does not tell you what is being bought and sold right now; you need four more things.
- Land — Is there only a promise to use it, or has a permit to build the facility been confirmed too?
- Business — Has a generation business license been obtained, and which procedures remain, such as whether an environmental impact assessment applies?
- Power grid — Is a possible connection still under discussion, or have the timing, reinforcement and cost been confirmed?
- Money and operation — What stage have the electricity buyer, the financing and construction reached, and if sales have begun, is there an operating record?
Mr. Park's field is still empty. Even for plans of the same size, when these four answers differ, what a buyer gets and the risk the buyer takes on differ too. The price on an empty field is not for panels that have yet to go up. It reflects how far the conditions for actually building a power plant have been put in place.
Words in this piece
- Generation licence A generation licence is the permit a person needs from the minister or a provincial governor to run a business that generates and sells electricity. Glossary → — the business permit obtained to run a generation business that produces and sells electricity.
- Grid connection Grid connection is the work of linking a new power plant to the network so its power can actually be delivered. Glossary → — the process of linking a power plant to the power grid so that it can send out the electricity it produces.
- PF (project financing) Project financing lends money on the strength of the cash a single project will earn, not on a company's credit. Glossary → — a financing method that weighs heavily the cash flow a project will generate in the future.
- PPA (Power Purchase Agreement) A PPA is a long-term power sale contract. In Korea the typical form is direct power trading (direct PPA): renewable power supplied to companies and others outside the power market. Glossary → — a contract in which generation companies or others and a buyer set the terms of a power trade.
- EPC (engineering, procurement and construction) EPC is a contract under which one company designs a power plant, buys its equipment, builds it and hands it over. Glossary → — engineering, procurement and construction bundled as one job.
- Project rights and equity — the bundle of rights to carry out a particular project, and ownership shares in the company that holds that project. You need to confirm exactly what is being traded.
Sources (4)
Sources
- LawMinistry of Government Legislation, Korean Law Information Center, *Electric Utility Act* (「전기사업법」), Art. 7 (effective 2026-09-18, checked 2026-10-30). Division between the minister and city or provincial licensing authorities, license standards, and the provision on gathering residents' views. ↩
- LawMinistry of Government Legislation, Korean Law Information Center, *National Land Planning and Utilization Act* (「국토의 계획 및 이용에 관한 법률」), Art. 56 (effective 2026-07-01, checked 2026-10-30). Installation of structures, changes to the form and quality of land, and the related exceptions. ↩
- LawMinistry of Government Legislation, Korean Law Information Center, *Environmental Impact Assessment Act* (「환경영향평가법」), Art. 22 (effective 2025-10-23, checked 2026-10-30). The specific types and scope of covered projects are delegated to the Enforcement Decree, so the rule does not apply uniformly. ↩
- LawMinistry of Government Legislation, Korean Law Information Center, *Electric Utility Act* (「전기사업법」), Art. 9 (effective 2026-09-18, checked 2026-10-30). Preparation period, commencement of business, and the distinction for reporting after an electricity generation business entity's first electricity trade. ↩