On a meeting-room whiteboard, 145 won and 155 won sit side by side: the prices per kWh named by the buyer and the seller. The gap is only 10 won, but if a factory buys 30 GWh a year for 15 years, it comes to 4.5 billion won. Using one set of assumed numbers, we trace which risks that 10 won is really the price of.

Published

4.5 billion won
What a 10-won gap in unit price adds up to over 15 years (assumed)
Contents (8)
  1. 01How does 10 won become 4.5 billion won?
  2. 02"But that's more than the SMP" — compared with what?
  3. 03Why the buyer can't easily sign
  4. 04Why the seller can't lower the price
  5. 05The 10 won is the price of four risk boxes
  6. 06Three places where one unit price leads you wrong
  7. 07What gets settled at the first meeting?
  8. 08Words in this piece

Two numbers sit side by side on a meeting-room whiteboard: 145 won and 155 won. They are the prices per kWh of electricity named by the buyer and by the seller.

Why 10 won weighs so muchExample numbers

The article’s worked assumption (30 GWh a year, 15 years, nominal).

© Renuary

The gap is only 10 won. Yet that 10 won can drag a negotiation out for weeks. To an onlooker, that seems strange. But suppose the factory buys 30 GWh a year for 15 years, and the math changes. Over 15 years, it comes to 4.5 billion won.

How does 10 won become 4.5 billion won?

All the numbers below are assumptions set for explanation, not market prices. Say a factory agrees to buy 30 GWh of renewable energy a year and sets the unit price at 150 won per kWh.

  • Amount bought per year: 30 GWh → 30 million kWh
  • Electricity payment per year: 30 million kWh × 150 won → 4.5 billion won
  • The same amount at the same price for 15 years: 4.5 billion won × 15 → 67.5 billion won

That is a contract worth 67.5 billion won in nominal terms, meaning the amount as is, without accounting for changes in prices.Source 1The contract volume of 30 GWh, the unit price of 150 won/kWh and the 15-year term are assumptions for explanation, not market prices. Calculation by Renuary.See in sources → Now change the unit price by just 10 won.

  • Per year: 30 million kWh × 10 won → 300 million won
  • Over 15 years: 300 million won × 15 → 4.5 billion won

The small gap on the whiteboard becomes 4.5 billion won over the full term of the contract. Yet 15 years is on the short side compared with large contracts made public in Korea.Source 3Hyundai Motor Group, press release (2024-10-30)610 GWh a year for 20 years (combined across 4 companies, company announcement)· SK Telecom, *Annual Report 2024* (English) PDF p.74See in sources →Source 6GS, *GS Wind to supply renewable energy to NAVERlargest onshore wind deal* (「GS풍력, 네이버에 재생에너지 공급…육상풍력 최대 규모」, 2026-04-22, company announcement; unofficial translation)See in sources →

Overseas, 15 years falls within the common range.Source 7EFET (European Federation of Energy Traders, now Energy Traders Europe), *EFET Insight into Renewable Power Purchase Agreements* (2022-03), p.1"usually between 7 and 15 years".See in sources → Gather the publicly disclosed terms, and they look like this.

WhoTermWhat was disclosed
Hyundai Motor Group (2024)20 years610 GWh a year (combined) from four generation companies
SK Telecom20 years from July 2027Solar PV electricity, price fixed for 20 years (amount not disclosed)
NAVER (2026)25 yearsDirect contract with a wind power company (GS Wind)
Renewable PPAs in EuropeUsually 7 to 15 years2022 material from the European Federation of Energy Traders (EFET)

Data company announcements by Hyundai Motor Group and SK Telecom, GS Wind news on the GS website, EFET (2022)© Renuary

Either way, the longer the term, the heavier the same 10 won becomes.

"But that's more than the SMP" — compared with what?

In the middle of a negotiation, someone says, "At 155 won, that's more than the SMP." It sounds plausible, but it leaves out what is being compared with what. There are at least four "electricity prices" you hear in renewable energy deals, and each is set in a different place by a different standard.

  • The wholesale price in the electricity market (SMP (System Marginal Price) SMP is the energy price set for each trading hour in the power market. It is the highest generation price among the generators eligible to set the price in that hour. Glossary →) — it changes every hour.
  • The price of a Renewable Energy Certificate (REC (Renewable Energy Certificate) A REC is the issuing and trading unit of a certificate proving renewable supply. Renewable generators earn income from selling RECs, apart from selling electricity. Glossary →) — the price of one certificate.
  • The unit price in a power purchase agreement (PPA (Power Purchase Agreement) A PPA is a long-term power sale contract. In Korea the typical form is direct power trading (direct PPA): renewable power supplied to companies and others outside the power market. Glossary →) — a price set by two companies.
  • The electricity tariff the factory actually pays to Korea Electric Power Corporation (KEPCO).

Even the units differ. The SMP, the PPA unit price and the electricity tariff are prices per kWh. The REC price is the price of one certificate carrying the value of "made from renewable energy" (the environmental attribute). These certificates are counted in units of 1 MWh of renewable electricity, multiplied by a REC weight (multiplier) A REC weight is the multiplier that awards more or fewer RECs for the same 1 MWh depending on the type and conditions of the plant. Glossary → that differs by facility.Source 2Korea Energy Agency, New and Renewable Energy Center, *Guide to REC Issuance and Weights* (「공급인증서(REC) 발급·가중치 안내」; unofficial translation)· *Guidelines for the Management and Operation of the Renewable Portfolio Standard and the Renewable Fuel Standard* (「재생에너지 공급의무화제도 및 연료 혼합의무화제도 관리ㆍ운영지침」; unofficial translation), appendix on REC weights.See in sources →

For solar PV on ordinary land (a general site), the weight is applied separately to each band of facility size.Source 4*Guidelines for the Management and Operation of the Renewable Portfolio Standard and the Renewable Fuel Standard* (「재생에너지 공급의무화제도 및 연료 혼합의무화제도 관리ㆍ운영지침」, Ministry of Climate, Energy and Environment Notice No. 2026-233, effective 2026-09-18; unofficial translation), Appendix 2, "Weights by Renewable Energy Source"solar PV on general sites: under 100 kW 1.2· from 100 kW 1.0· from above 3,000 kW 0.8; Note 4 (weights by band are applied separately across the total capacity) (Korean Law Information Center).See in sources →

Share of facility sizeWeight
Under 100 kW1.2
From 100 kW up to 3 MW1.0
Share above 3 MW0.8

Data *Guidelines for the Management and Operation of the Renewable Portfolio Standard and the Renewable Fuel Standard* (「재생에너지 공급의무화제도 및 연료 혼합의무화제도 관리ㆍ운영지침」; unofficial translation), Appendix 2© Renuary

So a small power plant under 100 kW gets 1.2 certificates for 1 MWh, and the bigger the plant, the fewer certificates it gets for each 1 MWh. Even for the same 1 MWh, how many certificates it earns depends on the facility.

So when you hear "more than the SMP," first make sure the pair matches. A PPA unit price is a price two companies set after weighing risks over many years; the SMP is the price of electricity set in the market for that hour. The two are set in different places and carry different risks.

Why the buyer can't easily sign

The corporate buyer's manager cannot sign on environmental performance alone. The price of electricity is a production cost.

Locking in the price for a long time frees the company from swings in future electricity tariffs. But if market electricity prices fall in the meantime, it ends up paying more. The same lock-in is a shield when prices rise and a shackle when they fall.

So the buyer looks at four things together: low total cost, stable supply over a long time, recognition of its renewable use record, and a way out if circumstances change.

Why the seller can't lower the price

The generation company's math starts from the other side. Building a power plant takes a lot of money, and much of that money is borrowed. A bank will lend only if there is a buyer at a set price for a long time.

Sign at too low a price, and nothing is left after paying principal and interest. So the seller looks for a fair unit price, a minimum return, and a reliable buyer who can pay throughout the contract term. While the buyer tries to protect its costs, the seller tries to protect its way of repaying debt.

The 10 won is the price of four risk boxes

Seen this way, the price negotiation is not a fight over whether something is expensive or cheap. It is about deciding who will bear what may happen in the future. On the negotiating table, the risks are laid out box by box.

  • Market price swings — if market electricity prices rise and fall sharply, who bears that risk?
  • Generation shortfall — if bad weather leaves generation short, who makes up the gap?
  • Curtailment Curtailment is an order to cut generator output when power is in surplus or the grid cannot carry it. It is a tool to keep supply and demand balanced and the grid stable. Glossary → — if the plant is stopped on the grid operator's orders, whose loss is it? The main legal provisions that set out curtailment contain no clause compensating for this loss.Source 5*Electric Utility Act* (「전기사업법」), Arts. 27-2 and 45; *Special Act on Activation of Distributed Energy* (「분산에너지 활성화 특별법」), Art. 16; *Standards for Maintaining Power System Reliability and Electricity Quality* (「전력계통 신뢰도 및 전기품질 유지기준」; unofficial translation), Art. 17there are grounds for curtailment and disconnection but no clause on compensating losses (Korean Law Information Center, checked 2026-10-02).See in sources → If the contract does not decide it, the box stays open.
  • The buyer's circumstances — if the corporate buyer scales back its factory partway through, what happens to the contract?

The direction is usually this: when the buyer takes on more of a box's risk, the unit price goes down; when the seller takes on more, the unit price goes up. The 10 won on the whiteboard is the difference in how these boxes are weighed on the scale.

Who bears the risk sets the price
Market priceOutput shortfallCurtailmentBuyer’s situationBuyerbears more → price ↓Sellerbears more → price ↑

Each contract splits these risks differently. The split shown is one example.

Three places where one unit price leads you wrong

In practice, drawing conclusions from the unit price alone often goes wrong. There are three snags.

  • Nominal versus real — 67.5 billion won and 4.5 billion won are amounts that do not account for inflation. A sum of 100 million won 15 years from now does not weigh the same as 100 million won today.
  • Unit price versus total cost — even with a low unit price, the company may have to make up a shortfall elsewhere at a higher price. Total cost can also flip depending on who pays the grid usage fee (the price of renting the power grid), commissions and taxes.
  • Same 155 won, different contract — if who bears the risk boxes differs, the same number is a different price.

So when comparing unit prices, lay out the risk boxes alongside them.

What gets settled at the first meeting?

Contracts like this are not settled at a first meeting. The task when the two sides first meet is not to set the price but to get a feel for which risks each side can bear.

There are four boxes to line up: timing (when supply starts), term, volume, and what happens when output falls short. As the meeting winds down, 145 and 155 are wiped off the whiteboard, and 30 GWh a year is written in the "volume" box. Below it, four new risk boxes are drawn. The 10 won will be written again only after those boxes are filled in.

Words in this piece

  • PPA (Power Purchase Agreement) A PPA is a long-term power sale contract. In Korea the typical form is direct power trading (direct PPA): renewable power supplied to companies and others outside the power market. Glossary → — a contract to buy a specific power plant's electricity at a set price for several years.
  • SMP (System Marginal Price) SMP is the energy price set for each trading hour in the power market. It is the highest generation price among the generators eligible to set the price in that hour. Glossary → — the wholesale price of electricity in the electricity market, set every hour.
  • REC (Renewable Energy Certificate) A REC is the issuing and trading unit of a certificate proving renewable supply. Renewable generators earn income from selling RECs, apart from selling electricity. Glossary → — a certificate that carries the value of "made from renewable energy" (the environmental attribute) and is bought and sold. It is priced separately from the electricity.
  • REC weight (multiplier) A REC weight is the multiplier that awards more or fewer RECs for the same 1 MWh depending on the type and conditions of the plant. Glossary → — a multiplier that gives more or fewer RECs for the same amount of electricity depending on the type of facility.
  • Curtailment Curtailment is an order to cut generator output when power is in surplus or the grid cannot carry it. It is a tool to keep supply and demand balanced and the grid stable. Glossary → — when there is surplus electricity, a power plant producing less on the grid operator's orders.
  • Grid usage fee — the price of renting the power grid.
Sources (7)

Sources

  1. The contract volume of 30 GWh, the unit price of 150 won/kWh and the 15-year term are assumptions for explanation, not market prices. Calculation by Renuary. ↩
  2. LawKorea Energy Agency, New and Renewable Energy Center, *Guide to REC Issuance and Weights* (「공급인증서(REC) 발급·가중치 안내」; unofficial translation)· *Guidelines for the Management and Operation of the Renewable Portfolio Standard and the Renewable Fuel Standard* (「재생에너지 공급의무화제도 및 연료 혼합의무화제도 관리ㆍ운영지침」; unofficial translation), appendix on REC weights. ↩
  3. ReleaseHyundai Motor Group, press release (2024-10-30) ↩610 GWh a year for 20 years (combined across 4 companies, company announcement)· SK Telecom, *Annual Report 2024* (English) PDF p.74 — 50 MW, 20 years from July 2027 (company announcement)· same company, *2024 Climate-related Disclosures Report* (English), p.16 — "at a fixed price for 20 years" (unit price and adjustment formula not disclosed).
  4. Law*Guidelines for the Management and Operation of the Renewable Portfolio Standard and the Renewable Fuel Standard* (「재생에너지 공급의무화제도 및 연료 혼합의무화제도 관리ㆍ운영지침」, Ministry of Climate, Energy and Environment Notice No. 2026-233, effective 2026-09-18; unofficial translation), Appendix 2, "Weights by Renewable Energy Source" ↩solar PV on general sites: under 100 kW 1.2· from 100 kW 1.0· from above 3,000 kW 0.8; Note 4 (weights by band are applied separately across the total capacity) (Korean Law Information Center).
  5. Law*Electric Utility Act* (「전기사업법」), Arts. 27-2 and 45; *Special Act on Activation of Distributed Energy* (「분산에너지 활성화 특별법」), Art. 16; *Standards for Maintaining Power System Reliability and Electricity Quality* (「전력계통 신뢰도 및 전기품질 유지기준」; unofficial translation), Art. 17 ↩there are grounds for curtailment and disconnection but no clause on compensating losses (Korean Law Information Center, checked 2026-10-02).
  6. GS, *GS Wind to supply renewable energy to NAVER ↩largest onshore wind deal* (「GS풍력, 네이버에 재생에너지 공급…육상풍력 최대 규모」, 2026-04-22, company announcement; unofficial translation) — "for the next 25 years," a wind farm scheduled to begin commercial operation in 2028.
  7. EFET (European Federation of Energy Traders, now Energy Traders Europe), *EFET Insight into Renewable Power Purchase Agreements* (2022-03), p.1 ↩"usually between 7 and 15 years".

Ask about this postQuestions shape the next pieces

Comments

  1. Loading…

Comments appear at once. Spam, abuse and personal data are removed. Two links at most.

Contents (8)

  1. 01How does 10 won become 4.5 billion won?
  2. 02"But that's more than the SMP" — compared with what?
  3. 03Why the buyer can't easily sign
  4. 04Why the seller can't lower the price
  5. 05The 10 won is the price of four risk boxes
  6. 06Three places where one unit price leads you wrong
  7. 07What gets settled at the first meeting?
  8. 08Words in this piece

All menus

Search

Articles

Data

Rules

History

Glossary

Renuary