The yearly total adds up, but the nights are empty — why 'amount' and 'time' must be read separately in renewable energy deals

A solar plant's yearly output can match a factory's yearly use, yet the factory runs at night and the solar plant rests. We follow which yardstick the same '100% renewable' was measured with, and what fills the gap.

Published

26.28 GWh
One year of generation from a 20 MW solar PV plant (assumed)
Contents (7)
  1. 01Why were the nights empty?
  2. 02How big is the gap?
  3. 03So what does this '100%' actually match?
  4. 04There are at least three yardsticks
  5. 05Three places where amount and time get mixed up
  6. 06What gets attached to next year's report?
  7. 07Words in this piece

A year-end report lands on the desk. Across the top, in large type: "100% renewable energy." The purchasing manager in charge of the factory nods. The electricity made last year by the solar plant the company signed a power purchase agreement (PPA (Power Purchase Agreement) A PPA is a long-term power sale contract. In Korea the typical form is direct power trading (direct PPA): renewable power supplied to companies and others outside the power market. Glossary →) with is almost the same as the amount the factory used over the year. On paper, it is 100%.

But lay the factory's power use over the plant's output hour by hour, and something looks off. In the afternoon, the plant makes more than enough. From sunset until dawn, almost nothing arrives. During those hours the factory ran on electricity from somewhere else. The yearly total added up, but the nights were empty.

Why were the nights empty?

Each kind of renewable energy makes electricity at different times. Solar PV makes it during the day, bunched around midday, and rests at night. Wind power follows the wind. It can generate at night too, but it swings from day to day. The factory, regardless, runs on its fixed shift schedule.

So even a contract whose yearly total adds up will, once split by the hour, show hours with a surplus and hours with a shortfall. That is why how to settle the surplus and what to fill the short hours with become important clauses in the contract.

Same yearly total, different hoursExample numbers
SolarFactory useNight: no outputNight: no output0h6h12h18h24h

Illustrative shape only. Even when yearly totals match, there is surplus at noon and a gap at night, filled by other plants, storage or other procurement.

How big is the gap?

For the sake of explanation, we set the numbers ourselves. They are all assumptions, and this is not the same plant as in the opening scene. The factory uses 30 GWh a year. A 20 MW solar plant with a Capacity Factor Capacity factor is the ratio of how much a plant actually generated to the maximum it could have produced. Plants of the same size can deliver very different output depending on their capacity factor. Glossary → of 15% makes about 26.28 GWh a year (20 MW × 8,760 hours × 0.15). That is 26-odd of the 30 the factory uses, short of nine in ten.Source 3The factory's 30 GWh, the 20 MW plant and the 15% capacity factor are assumptions for explanation. Calculation by Renuary.See in sources →

The capacity factor is the ratio of what a plant actually made to what it would have made running at full output all year long. Turn 15% into a single day and it becomes tangible. Multiply 24 hours by 0.15 and you get 3.6 hours: about as much as running at full output for 3.6 hours a day.Source 4The 15% capacity factor in the text is an assumption for explanation. For reference, Korea Energy Economics Institute Basic Research Report 2024-22, Table 5-1 (printed p.46), set the solar PV capacity factor at 15.4% when calculating generation costs (onshore wind 23%, offshore wind 29.4%). It is a calculation premise of the report, not an observed statistic.See in sources →

In reality, the plant generates in a rise and fall from sunrise through midday, and makes almost nothing after sunset. For a factory that runs day and night, a large part of the hours it uses power are hours without sun. Under these assumptions the yearly total falls a little short, and measured by the hour, the gap is far larger.

So what does this '100%' actually match?

The manager looks at the report again. Is this 100% a wrong number? No. It simply matches something different.

Think of a household account book. One kind balances a year's income and spending once, at year-end. Another lets you spend only out of the money that has come in at each moment. Both say "balanced," but they mean different things. Renewable energy is the same. One kind of matching compares how much was made with how much was used over a year. Another checks whether that much renewable energy was being made at the very hour the factory was using power.

Today, companies mostly count their results the first way, by the yearly total. Korean RE100 (K-RE100), the Korean program that recognizes the renewable energy a company uses as its result, also recognizes results year by year.Source 1Korea Energy Agency, New and Renewable Energy Center, *K-RE100 Guide* (「K-RE100 안내」; unofficial translation)· Ministry of Climate, Energy and Environment, *Regulation on Support for Renewable Energy Facilities, etc.* (「재생에너지 설비의 지원 등에 관한 규정」, Notice No. 2026-272, effective 2026-10-27; unofficial translation), Art. 66 (the minister runs the program)· Art. 67(1) (the New and Renewable Energy Center as the dedicated agency)· Art. 68-2(1) (ways of using renewable electricity).See in sources → Despite the similar name, it is separate from the international RE100 campaign: a Korean program the government runs by ministerial notice. Whether a report's 100% is an RE100 number or a K-RE100 number differs from report to report. Its meaning becomes clear only when the number says which one it is. What the two share is that both count by the year, and that the routes K-RE100 recognizes are all renewable electricity.Source 1Korea Energy Agency, New and Renewable Energy Center, *K-RE100 Guide* (「K-RE100 안내」; unofficial translation)· Ministry of Climate, Energy and Environment, *Regulation on Support for Renewable Energy Facilities, etc.* (「재생에너지 설비의 지원 등에 관한 규정」, Notice No. 2026-272, effective 2026-10-27; unofficial translation), Art. 66 (the minister runs the program)· Art. 67(1) (the New and Renewable Energy Center as the dedicated agency)· Art. 68-2(1) (ways of using renewable electricity).See in sources → The report's 100% is a number read off this scale.

There are at least three yardsticks

Among companies with factories or data centers that run around the clock, some are interested in the second way: matching hour by hour. Abroad this is called "24/7." It means matching the electricity used in every hour, 24 hours a day, 7 days a week, with carbon-free electricity (electricity that emitted no carbon when it was made). The United Nations (UN) also runs the 24/7 Carbon-Free Energy Compact, which sets out this principle. It is not a Korean program.Source 2UN Energy, *24/7 Carbon-free Energy Compact*.See in sources →

There is a reason for writing "carbon-free" here rather than "renewable." The technical criteria of the coalition behind this goal (the 24/7 Carbon-Free Coalition) recognize nuclear power, which the RE100 criteria do not count as renewable, as carbon-free electricity.Source 524/7 Carbon-Free Coalition, *24/7 Carbon-Free Electricity technical criteria and appendices* (v1.03, 2026-07-09· first published 2025-05-29), p.9"While it is not classified as renewable under the RE100 technical criteria, the 24/7 Carbon-Free Coalition recognises nuclear power as a source of carbon-free electricity".See in sources → So nuclear electricity does not count toward renewable results on the RE100 technical criteria yardstick, but on the 24/7 yardstick it fills hours.

There are at least three yardsticks for reading the word "100%." The first two measure how much renewable or carbon-free electricity was used; the third, Scope 2, records greenhouse gas emissions on the books, so it is a different kind of thing.

  • RE100 RE100 is a voluntary campaign in which companies pledge to source 100% of their electricity from renewables. Glossary → is an international campaign that companies join by their own declaration. It counts results by the yearly total. The certificates' generation date only has to be reasonably close to the reporting year of that year's consumption.Source 6Climate Group, *RE100 Technical Criteria* (version 5.0, published 2025-03-24), §6 Vintage limitations"the vintage of the attributes … must be reasonably close to the reporting year of the electricity consumption".See in sources → Its scale has one mark per year.
  • 24/7 is a voluntary goal of matching hour by hour. Its scale has a mark for every hour, and it counts nuclear too.
  • Scope 2 is the line, in the international standard for recording a company's greenhouse gas emissions on the books (the GHG Protocol), that counts the emissions from using purchased electricity. How this line is counted is under discussion for revision. Where its marks go is still a question mark.

The same '100% renewable' means different things depending on which yardstick measured it.

Same 100%, different scalesExample numbers
RE100Annual total24/7Voluntary, every hourScope 2 methodUnder revision? ? ?

The tick counts are illustrative. Ask which ruler a “100%” was measured with.

Three places where amount and time get mixed up

When "amount" and "time" get mixed up, numbers are easy to misread. There are three places where this trips people up.

First, annual GWh says nothing about time. "26 GWh a year" is only how much is made in a year; it does not tell you at what hour that electricity comes.

Second, the 15% capacity factor is an assumption. It differs by plant and by year. The value an official report uses in its cost calculations is also a premise, not a measured statistic.

Third, which yardstick the report's 100% was measured with. RE100's yearly total and 24/7's hourly matching read the same number differently.

More than MW or annual GWh, when that electricity comes shows the real shape of the contract.

What gets attached to next year's report?

There are a few ways to fill the gap. Add other plants, store surplus electricity in an energy storage system (ESS) and use it at night, or cover the short hours with procurement of another kind. An operator that bundles several plants to supply power can mix many small solar plants with wind power to bring the supply closer to a large factory's demand, evening out the shape of the day a little.

Still, every plant that goes into the bundle needs three things: the right to sell that electricity (sales rights), a way to measure when and how much it made (metering), and an agreement on how to divide the money for the surplus and shortfall (settlement terms).

So when the plant side says, "We can supply 26 GWh a year," the buyer has two more questions to ask about time. To a plant: "When in the day does that come?" To a supplier that bundles several plants: "How do you handle the short hours and the surplus hours?"

At the end of the next year, the manager writes three lines next to the report's "100%." Can this plant's electricity travel along the wires (the power grid) to our factory? Who holds the right to sell that electricity now, and is it not already tied up elsewhere? And does that electricity come at the hours the factory uses power? Even with a "yes" on the first two lines, the third line keeps a few hours of the night blank. The "100%" at the top of the report stays as it is. Of the three lines below it, only the last has not yet filled the hours after sunset. And on the third yardstick, a question mark still sits where the marks should be.

Words in this piece

  • Capacity Factor Capacity factor is the ratio of how much a plant actually generated to the maximum it could have produced. Plants of the same size can deliver very different output depending on their capacity factor. Glossary → — the ratio of the electricity a plant actually made to what it would have made running at full output without a break.
  • MW and MWh MW (megawatt) and MWh (megawatt-hour) are kW and kWh scaled up to the mega unit. They are used for large values such as plant size or power market volumes. Glossary → — MW is the size of a plant (the power of an engine); MWh is the amount it actually made with that power (the distance driven). A GWh is a thousand MWh.
  • PPA (Power Purchase Agreement) A PPA is a long-term power sale contract. In Korea the typical form is direct power trading (direct PPA): renewable power supplied to companies and others outside the power market. Glossary → — a contract in which a company that will buy electricity and a power plant set the volume and price for a number of years.
  • ESS (energy storage system) An ESS stores electricity and releases it when needed. Korean law calls it an 'electricity storage device'. Glossary → — an energy storage system that holds surplus electricity and releases it at the hours it is needed.
  • 24/7 — a voluntary goal of matching the electricity used every hour with carbon-free electricity.
Sources (6)

Sources

  1. LawKorea Energy Agency, New and Renewable Energy Center, *K-RE100 Guide* (「K-RE100 안내」; unofficial translation)· Ministry of Climate, Energy and Environment, *Regulation on Support for Renewable Energy Facilities, etc.* (「재생에너지 설비의 지원 등에 관한 규정」, Notice No. 2026-272, effective 2026-10-27; unofficial translation), Art. 66 (the minister runs the program)· Art. 67(1) (the New and Renewable Energy Center as the dedicated agency)· Art. 68-2(1) (ways of using renewable electricity). ↩
  2. UN Energy, *24/7 Carbon-free Energy Compact*. ↩
  3. The factory's 30 GWh, the 20 MW plant and the 15% capacity factor are assumptions for explanation. Calculation by Renuary. ↩
  4. DataThe 15% capacity factor in the text is an assumption for explanation. For reference, Korea Energy Economics Institute Basic Research Report 2024-22, Table 5-1 (printed p.46), set the solar PV capacity factor at 15.4% when calculating generation costs (onshore wind 23%, offshore wind 29.4%). It is a calculation premise of the report, not an observed statistic. ↩
  5. 24/7 Carbon-Free Coalition, *24/7 Carbon-Free Electricity technical criteria and appendices* (v1.03, 2026-07-09· first published 2025-05-29), p.9 ↩"While it is not classified as renewable under the RE100 technical criteria, the 24/7 Carbon-Free Coalition recognises nuclear power as a source of carbon-free electricity".
  6. DataClimate Group, *RE100 Technical Criteria* (version 5.0, published 2025-03-24), §6 Vintage limitations ↩"the vintage of the attributes … must be reasonably close to the reporting year of the electricity consumption".

Ask about this postQuestions shape the next pieces

Comments

  1. Loading…

Comments appear at once. Spam, abuse and personal data are removed. Two links at most.

Contents (7)

  1. 01Why were the nights empty?
  2. 02How big is the gap?
  3. 03So what does this '100%' actually match?
  4. 04There are at least three yardsticks
  5. 05Three places where amount and time get mixed up
  6. 06What gets attached to next year's report?
  7. 07Words in this piece