Expected-profit settlement
constrained-off payment
Expected-profit settlement pays a unit that was in the day-ahead schedule but turned down by KPX the profit it would have made had it run.
The market rules compute it as market-price revenue minus variable cost for the energy not generated. Since no fuel was burned, the unit gets the margin, not the full sales value.
On Jeju, a renewable bidding scheme began as a pilot in June 2024, and participating renewable plants receive this payment too. The government says this is distinct from compensating time-of-day curtailment; it is not a general curtailment compensation scheme.