Figure · re-grid-queue

38,065 MW of applications — where they stand (May 2026)

Of 38,065 MW of renewable connection applications, 3,546 MW wait without a slot — 64.8% of it in Honam.

38,065 MW of applications — where they stand (May 2026)
Applications 38,065 MWConnected 29,382Building 5,137Waiting, no slot 3,546of which Honam 2,298 (64.8%)MW

Press release from Rep. Kim Wi-sang’s office (6 Oct 2026, citing data from the Korea Energy Agency and KEPCO; note 3).

In words

A single stacked bar. The 38,065 MW of connection applications split three ways: 29,382 MW connected, 5,137 MW with a slot and under construction, 3,546 MW waiting with no slot. Under the waiting segment, the Honam share — 2,298 MW (64.8%) — is marked separately. As of May 2026.

Data
Press release from Rep. Kim Wi-sang’s office (6 Oct 2026, citing data from the Korea Energy Agency and KEPCO; note 3) — original table not seen (2026-05)
Rights
© Renuary · reuse terms pending (opens as CC BY 4.0 once sources are checked)
Used in
More power plants, but no electricity to buy — three layers of shortage: wires, owners and time
Download
PNG · SVG — the source, address and rights line is printed under the figure