- 3,546 MW
- Capacity waiting for connection because there is no room on the lines
Contents (7)
An imagined scene. A farming family in South Jeolla Province built a small solar power plant on the land next to its rice paddy. The ground has been leveled, the permit obtained and the panels put up, so all that is left is to hook it up to the lines of KEPCO (Korea Electric Power Corporation). But the answer that comes back is "there is no room right now." The panels are ready to catch the sun, but the door that would let the power out will not open.
Hooking a power plant up to the power grid is called Grid connection Grid connection is the work of linking a new power plant to the network so its power can actually be delivered. Glossary →. Building and connecting are different jobs, and many projects are now stuck at the second. Where does that line get blocked, and is every project standing in it real? What do you have to give up to get in early?
How long is the connection line?
Connection goes in order. When a developer applies to KEPCO for connection, KEPCO checks whether the road that power would travel has room. If it does, a construction schedule is set; if not, the project goes on the waiting list.
There is a number that shows how long this line is. The size of generating equipment is measured in MW (megawatts): how much power it can put out at once. According to a press release from the office of National Assembly member Kim Wi-sang, citing data received from KEPCO and the Korea Energy Agency, 3,546 MW of capacity is waiting for connection because the lines are short of room, and 2,298 MW of it (64.8%) is concentrated in the Honam region. Capacity that has already been given a spot and is under construction is not included in this figureSource 1Office of National Assembly member Kim Wi-sang, *"3.5 GW of Renewables Waiting for Connection, 65% Concentrated in Honam…"* (「재생에너지 접속대기 3.5GW, 65%가 호남에 몰려…」, press release, 2026-10-06; unofficial translation), citing data submitted by KEPCO and the Korea Energy Agencywaiting for connection 3,546 MW· Honam region 2,298 MW (64.8%)· 5,137 MW under construction counted separately. Version posted by the Korea Law Consumers Federation (unofficial translation).See in sources →.
How big 3,546 MW is becomes clear when set against the solar limit a single Substation A substation is a site with equipment that raises or lowers the voltage of electricity and passes it on to the next part of the grid. Glossary → can take. The limit per substation that the government has decided to raise from 2027 is 60 MWSource 2Ministry of Climate, Energy and Environment, *Overhauling the Power Grid System to Accommodate 100 GW or More of Renewable Energy by 2030* (「2030년 재생에너지 100GW 이상 수용하도록 전력망 체계 혁신한다」, press release, distributed 2026-09-28; unofficial translation), p. 2 and p. 13distribution line 14→16 MW· substation 50→60 MW· Honam +2.6 GW· effective January 2027. Version posted by the KDI Economic Information and Education Center. "About 59" is a rough estimate from 3,546 ÷ 60.See in sources →. Divide the waiting volume by that limit to gauge its size alone, and it is enough to fill about 59 new substations to the brim. It is a division done just to get a sense of how long the line is.
Is every project in the line real?
There is a common misconception: that the connection backlog comes from KEPCO's construction running late. The government's own document points to another cause as well. Because grid capacity has been handed out free, in the order applications came in, some of it is held by projects that will actually arrive late and are just keeping their place. The document called this "power grid squatting"Source 3Same press release as [2], p. 10free first-come, first-served allocation and "power grid squatting."See in sources →.
The example is offshore wind in Honam. This is the story of projects outside the waiting line that secured their spots first and are running late. When such holdings occupy the grid, solar projects that could be built early end up in the waiting line. The government wrote that 15.8 GW of connection rights, the right to a reserved spot on the grid, had been secured through 2030, but about 3 GW is expected to actually come in by then (1 GW is 1,000 MW)Source 4Same press release as [2], p. 17Honam offshore wind connection rights of 15.8 GW through 2030, with about 3 GW expected to actually come in· Same document: offshore wind has claimed the grid in advance, so solar that could come in soon is left waiting for connection.See in sources →. Of five parcels that have reserved a front-row spot, four look as if they will not even be packed by then. Not every delayed project is a phantom. Since 2024, the government has taken back about 9 GW of connection rights from phantom projects, meaning projects that will never actually be builtSource 5Same press release as [2], p. 3about 9 GW of connection rights taken back from phantom projects since 2024.See in sources →.
Bars share one scale. Both figures are from the ministry press release of 28 Sep 2026; about 3 GW is a projection.
At which road's entrance does it get blocked?
The road electricity takes to reach a home resembles a parcel delivery route. Transmission lines are the highway where big trucks run, substations are the logistics hubs where loads are split up, and the neighborhood Distribution line / distribution network The distribution network carries electricity from substations to neighbourhoods, homes and factories; each circuit in it is a distribution line. Glossary → is the side streets where small delivery vans go. Neighborhood solar hooks up to those side streets, that is, to a single low-voltage line (a distribution line). Since it is like sending parcels out from a side street, there has to be room at all three points: the side-street entrance (the distribution line), the logistics hub entrance (the substation), and the highway on-ramp (the Transmission Grid The transmission grid is the lines and substations carrying power from plants far at high voltage. It is the trunk road between where power is made and where it is used. Glossary →). A large power plant of 40 MW or more gets straight onto the highway, so only the transmission grid matters for itSource 6Same press release as [2], p. 10connection at the distribution level needs room on the distribution grid, the substation and the transmission grid; connection at the transmission level for 40 MW or more needs the transmission grid.See in sources →. A plant smaller than that threshold passes through three entrances; a large plant passes through one.
A plant on the distribution network needs room on the line, the substation and the transmission grid. 40 MW and above needs only transmission (note 6).
There is one number, though, that looks odd at first glance. According to the government's document, distribution lines that mostly carry solar are used, on a one-year average, at a rate (utilization rate) of about 15%Source 7Same press release as [2], p. 10 and p. 14utilization rate of solar-heavy distribution lines about 15%· connection capacity calculated against peak times that add up to only a few hours a year.See in sources →. In Korean this shares its name with a power plant's capacity factor, which compares what a plant actually made with what it would have made running at full output all year, but it is a different yardstick. Here it measures how full the line was on average over a year.
It sounds like saying the lines are too full to connect to while they actually sit mostly empty. The two do not contradict each other. The utilization rate is a one-year average, while the connection limit is set so as not to exceed the busiest moments, which add up to only a few hours a year, the government's document says. Solar output bunches into the few hours of strong sun, so if the entrance is closed to guard against those moments, the line sits empty for the long remainder.
One way out is to agree to cut output during the rare moments of overflow and open the entrance a little wider. That is the idea behind Flexible (non-firm) connection A flexible connection lets more generation onto the grid than its hosting capacity, on the condition that it is curtailed first when the grid overloads. Glossary →. The government's measures start from here too.
The curve is a concept sketch, not measured data. The 15% figure is distribution-line utilization from the government document (note 7).
Which entrance did the government open first?
The measures the government put out in September 2026 touch these three entrances one by one. First, it widened the limits a little. The solar that can be connected to one distribution line goes up from 14 MW to 16 MW, and one substation from 50 MW to 60 MW. The distribution line change takes effect from January 2027 and the substation change in the first half of that year, and the government expects this to let Honam take in 2.6 GW moreSource 2Ministry of Climate, Energy and Environment, *Overhauling the Power Grid System to Accommodate 100 GW or More of Renewable Energy by 2030* (「2030년 재생에너지 100GW 이상 수용하도록 전력망 체계 혁신한다」, press release, distributed 2026-09-28; unofficial translation), p. 2 and p. 13distribution line 14→16 MW· substation 50→60 MW· Honam +2.6 GW· effective January 2027. Version posted by the KDI Economic Information and Education Center. "About 59" is a rough estimate from 3,546 ÷ 60.See in sources →. The government said this increase would be done through flexible connection. So capacity that connects early this way will be the first to cut output when the grid overflowsSource 8Same press release as [2], p. 13limit increase through flexible connection· flexibly connected capacity curtailed first.See in sources →. It is a trade: the price of getting in early is moving up the order for Curtailment Curtailment is an order to cut generator output when power is in surplus or the grid cannot carry it. It is a tool to keep supply and demand balanced and the grid stable. Glossary →, that is, being instructed to generate less when there is surplus power.
Next come the locked substations. A substation locked so that it accepts no new connections is called a Grid-managed substation A grid-managed substation is one designated as saturated, where new generation is barred from connecting. Glossary → (unofficial translation). In the Honam region this designation was lifted as of October 1, 2026, and new connection applications will be accepted from January 2027. Of Honam's 87 substations, 46 can take connections right away, and the 41 that are already full will open in turn in 2028–2030Source 9Same press release as [2], p. 1 and p. 23Honam region grid-managed substations released on 2026-10-01, new applications from 2027-01· of Honam's 87 substations, 46 immediately, 41 saturated ones in stages over 2028–2030.See in sources →.
Finally, the way projects line up will change. There is a system under which generation companies designated by the government must meet a set share of their generation with renewable energy: the RPS (Renewable Portfolio Standard) RPS obliges designated generators and others to supply a share of their generation from renewables. They meet it by generating it themselves or buying RECs. Glossary →. From January 2027, projects that win bids in this system's competitive bidding will be given connection rightsSource 10Same press release as [2], p. 3connection rights for projects winning RPS competitive bidding from January 2027.See in sources →. The government also said it would weigh whether projects were actually built and reflect that in allocating grid spots from 2031 onSource 11Same press release as [2], p. 3project delivery record reflected in allocation from 2031 on.See in sources →. The point is to give the spot to those who will actually build rather than to those who applied first.
What to check when you pass these numbers on
"MW" comes up again and again in connection stories, but each number counts something different.
- 3,546 MW is a figure from a lawmaker's office press release citing data submitted by KEPCO and the Korea Energy Agency. Capacity that has already been given a spot and is under construction is not included.
- "About 59 substations" is a rough estimate from dividing the waiting volume by the 2027 limit of 60 MW. In reality, the remaining room differs from substation to substation.
- Honam's +2.6 GW and offshore wind's "about 3 GW" are government projections. They are not amounts already built.
Waiting volume, secured connection rights and the volume that will actually come in are different numbers in the same unit.
How long will the farming family from the start have to wait?
The situation in Honam before these measures fits in one sentence. The government wrote that new projects seeking to join the grid were in "a situation where it would only be possible after 2034"Source 12Same press release as [2], p. 1new projects in Honam "only possible after 2034" (before the measures).See in sources →. That means if the imagined farming family from the opening had applied in 2026, it would have had to wait at least 8 years.
How far the measures will pull that clock forward is not yet known. The higher limits and the lifting of the substation designation take effect from 2027, and the 41 full substations will open in turn through 2030Source 9Same press release as [2], p. 1 and p. 23Honam region grid-managed substations released on 2026-10-01, new applications from 2027-01· of Honam's 87 substations, 46 immediately, 41 saturated ones in stages over 2028–2030.See in sources →. If big transmission lines are not laid in the meantime, the highway on-ramp will be blocked again.
When you see the words "connection backlog" in the news, three questions will do. Is the blockage at the distribution line, the substation or the transmission grid? Will the projects in line actually be built? What is given up in return for getting in early? A power plant that is ready to make electricity but has no entrance to send it through is caught somewhere among these three questions.
Words in this piece
- Grid connection Grid connection is the work of linking a new power plant to the network so its power can actually be delivered. Glossary → — hooking a new power plant up to the power grid so that the electricity it makes can actually be sent out.
- Distribution line / distribution network The distribution network carries electricity from substations to neighbourhoods, homes and factories; each circuit in it is a distribution line. Glossary → — the low-voltage web of lines that carries power, stepped down at a substation, out to homes and shops in the neighborhood. Each of those lines is a distribution line, and small solar plants hook up here.
- Flexible (non-firm) connection A flexible connection lets more generation onto the grid than its hosting capacity, on the condition that it is curtailed first when the grid overloads. Glossary → — a way of joining the grid earlier by agreeing to be the first to cut output during the rare moments when the grid overflows.
- Grid-managed substation A grid-managed substation is one designated as saturated, where new generation is barred from connecting. Glossary → — a substation locked so that it accepts no new connections.
- Curtailment Curtailment is an order to cut generator output when power is in surplus or the grid cannot carry it. It is a tool to keep supply and demand balanced and the grid stable. Glossary → — a power plant generating less on the grid operator's instruction when there is surplus power.
- RPS (Renewable Portfolio Standard) RPS obliges designated generators and others to supply a share of their generation from renewables. They meet it by generating it themselves or buying RECs. Glossary → — a system that requires generation companies designated by the government to meet a set share of their generation with renewable energy.
Sources (12)
Sources
- ReleaseOffice of National Assembly member Kim Wi-sang, *"3.5 GW of Renewables Waiting for Connection, 65% Concentrated in Honam…"* (「재생에너지 접속대기 3.5GW, 65%가 호남에 몰려…」, press release, 2026-10-06; unofficial translation), citing data submitted by KEPCO and the Korea Energy Agency ↩waiting for connection 3,546 MW· Honam region 2,298 MW (64.8%)· 5,137 MW under construction counted separately. Version posted by the Korea Law Consumers Federation (unofficial translation).
- ReleaseMinistry of Climate, Energy and Environment, *Overhauling the Power Grid System to Accommodate 100 GW or More of Renewable Energy by 2030* (「2030년 재생에너지 100GW 이상 수용하도록 전력망 체계 혁신한다」, press release, distributed 2026-09-28; unofficial translation), p. 2 and p. 13 ↩distribution line 14→16 MW· substation 50→60 MW· Honam +2.6 GW· effective January 2027. Version posted by the KDI Economic Information and Education Center. "About 59" is a rough estimate from 3,546 ÷ 60.
- ReleaseSame press release as [2], p. 10 ↩free first-come, first-served allocation and "power grid squatting."
- ReleaseSame press release as [2], p. 17 ↩Honam offshore wind connection rights of 15.8 GW through 2030, with about 3 GW expected to actually come in· Same document: offshore wind has claimed the grid in advance, so solar that could come in soon is left waiting for connection.
- ReleaseSame press release as [2], p. 3 ↩about 9 GW of connection rights taken back from phantom projects since 2024.
- ReleaseSame press release as [2], p. 10 ↩connection at the distribution level needs room on the distribution grid, the substation and the transmission grid; connection at the transmission level for 40 MW or more needs the transmission grid.
- ReleaseSame press release as [2], p. 10 and p. 14 ↩utilization rate of solar-heavy distribution lines about 15%· connection capacity calculated against peak times that add up to only a few hours a year.
- ReleaseSame press release as [2], p. 13 ↩limit increase through flexible connection· flexibly connected capacity curtailed first.
- ReleaseSame press release as [2], p. 1 and p. 23 ↩Honam region grid-managed substations released on 2026-10-01, new applications from 2027-01· of Honam's 87 substations, 46 immediately, 41 saturated ones in stages over 2028–2030.
- ReleaseSame press release as [2], p. 3 ↩connection rights for projects winning RPS competitive bidding from January 2027.
- ReleaseSame press release as [2], p. 3 ↩project delivery record reflected in allocation from 2031 on.
- ReleaseSame press release as [2], p. 1 ↩new projects in Honam "only possible after 2034" (before the measures).