SMP merit-order simulator
Capacities are actual (KPX 2025). Costs are illustrative — actual unit variable costs are not public.
Price set by: Coal
Read as supply and demand: the steps are the supply curve, cheapest first; the dashed line is demand (held fixed whatever the price, in this tool); the orange dot is where they meet — its height is the SMP.
| Source (cheapest first) | Capacity | Cost (illustrative) | Running |
|---|---|---|---|
| Renewablesreflected separately in the day-ahead plan first | 19.5 GW | 0 | 19.5 GW |
| Nuclear | 26.1 GW | 10 | 26.1 GW |
| Coal | 41.7 GW | 90 | 34.5 GW |
| LNG | 48.4 GW | 150 | 0 GW |
| Oil | 0.5 GW | 250 | 0 GW |
Not in this calculation
Using the example values
Tool: Renuary (CC BY 4.0) · Numbers are examples. Method and limits on the original page.