This is the per-hour, per-megawatt reward set so a reference plant can recover its net cost of entry under standard conditions.

Net cost of entry is the plant's annualised fixed cost less the profit it expects from the market, and this price is the starting point for capacity payments.

The rules have the cost evaluation committee decide it, with an adjustment factor if needed.